Hi Mahesh,

 

If there is a major difference, then what can be the probable cause of this ?

 

I tried to replicate the same in our system and found that the Change ID depends on the number of changes happening to a single status.

 

For example, if you change the Status of the Sales Order from In Process to Completed then after the initial number they will be as follows

 

In the Table CRM_JEST - The Completed user Status is E004 and it has been changed 2 times. So, initial number was 1 followed by 2 more changes. So the final change number will be 3.

 

Open --> In Process --> Completed --> In Process --> Completed

 

CRM_JEST Table.PNG

And in the Change Table the status E004 should be 3

CRM_JSDC Table.PNG

 

So, check the entries in the table and try to replicate the same in a development or quality system. The system status which is dependent on your user status changes based on the user status. You can check the same with the status with the 'I'.

 

So, try to figure out the big delta and what might have caused the same. If there are no possible changes found then we can manually change the entries as a last step. But again carefully check the entries with the proper header GUID ID.

 

Hope this will help.

 

Thanks and Regards,

Samantak Chatterjee.